Works on return to service of electric towers refurbished at Nsimalen

Eneo Cameroon informs its customers at Nsimalen, Mbalmayo , Mfou , Ebolowa, Sangmelima  and environs that its teams will carry out, on Sunday 21 January 2018 from 6am to 6pm, works on the switch-over of the Ahala-Mbalmyo transmission line to the new towers built at Nsimalen

These towers will be introduced into the network thereby replacing those that were vandalized in July 2016.

At the same time, reinforcement work on the Mbalmayo –Ebolowa line will continue.

During the execution of works, electrical service will be interrupted or disrupted at Nsimalen Mbalmayo, Mfou, Ebolowa, Sangmelima and environs. Measures have been taken to ensure continuity of service at the Nsimalen International Airport and the Pumping Station at Akomnyada.

For further information, safety and energy saving tips visit our website: www.eneocameroon.cm or call our Customer Care Centre at 8010