13 January 2016 Annoucement : Eneo is relaunching reinforcement works on the Logbaba-Bassa-Deido-Bonaberi transmission line

Eneo Cameroon hereby announces the relaunch   of the second phase of reinforcement works on the 90 KV transmission line of the Douala region between Bassa and Deido.

These works that began on 30 November 2015 was suspended on 17 December 2015 due to end of year festivities. The works would last 2 weeks as from 14 January.  

As a reminder, phase 1 that has been completed allowed for the increase in energy transit and the improvement of supply in a safe manner on the Logbaba-Bassa stretch.

Throughout the period of execution, from 14 to 28 January 2016, certain localities of the Littoral Region i.e. Bonaberi, South-West, West, North-West will witness disruptions in electricity supply in the evening; ranging from 2 to 3 times a week. 

However, measures have been taken to lessen as much as possible inconveniences for households and businesses.

In order to better manage this period, please consult the rotating distribution program and our safety and energy saving tips on our website: www.eneocameroon.cm or call 8010.

Peter Nkeih
COO Technical Activities

 